What is SMV in garments? How sewing minutes set your price and delivery date

SMV (standard minute value) is the number of minutes a garment takes to sew. What it means, typical values for T-shirts and polos, how factories turn SMV and line efficiency into your price and your delivery date, and what to ask before you order.

SR Santosh Rijal
Founder, Trishakti Apparel
Published 4 min read

Get a line-by-line quote

SMV, the standard minute value, is how many minutes a garment takes to sew. It sounds like an internal factory number, but it decides two things you care about: the making part of your price, and how many days your order needs on the line. Here is what it means, and what to ask a factory before you order.

What does SMV mean?

SMV is the time a trained operator needs to complete one operation, such as attaching a sleeve, at a normal working pace, usually with allowances included for rest and machine handling. Add up the SMV of every operation and you have the minutes needed for one garment. You will also see SAM (standard allowed minute). Often it means the same thing, but some factories quote SMV before allowances, so ask whether allowances are included; SAM vs SMV explained.

How many minutes does a T-shirt or polo take?

Published reference values put a basic round-neck T-shirt at about 8 to 8.5 minutes and a short-sleeve polo somewhere between about 10 and 15 minutes, and the same garment can differ widely between factories and styles. Online Clothing Study lists a crew-neck T-shirt at about 8 minutes (range 6–12) and a polo at about 15 (range 10–20); the Scan ERP reference table gives 8.5 and 10.4. Every extra detail adds operations and minutes:

  • back-neck tape or shoulder-to-shoulder tape
  • side seams instead of a tubular body
  • a placket, collar or pocket
  • contrast binding, a split hem, extra labels

That is why two “basic” tees can carry different making costs. A polo takes longer than a tee mostly because of its placket and collar.

What is line efficiency?

SMV assumes ideal conditions: the bundle is already beside the operator, the machine runs, the operator knows the style. Real lines lose time to style changeovers, waiting for work, machine breakdowns and absence. Line efficiency measures how much of the worked time turned into standard minutes:

Line efficiency = (pieces produced × SMV) ÷ (operators × minutes worked) × 100

Factories usually plan production at around 60–80% efficiency, not 100% (why factories plan at 60–80%; Online Clothing Study). A factory that promises dates as if its line ran at 100% will miss them.

How does SMV set your price?

The making part of a garment price is roughly:

Making cost ≈ SMV × the factory’s cost per minute ÷ its line efficiency

Here the cost per minute is the cost of one worked minute on the floor, wages and everything else, before any efficiency adjustment. (Some factories build efficiency into their cost per minute instead; then you do not divide by it again.) So a style with more minutes costs more to make, and a factory with low efficiency spreads its costs over fewer pieces. Fabric is still usually the bigger line on a knit garment’s costing sheet; see our costing sheet explained. For the factory-side maths, see SMV costing for CMT pricing.

How does SMV set your delivery date?

A line’s daily output is its productive minutes divided by the garment’s SMV. As an illustration: a line of 40 operators on a 480-minute shift at 70% efficiency has 40 × 480 × 0.70 = 13,440 productive minutes a day. At 8.5 minutes a T-shirt, that is about 1,580 T-shirts a day. Add details that raise the SMV, and the same line makes fewer pieces a day, so your order needs more days. This is an illustration of the method, not a promise of output for any one factory.

What should you ask a factory?

  1. What SMV did you use for my style, and which operations does it include?
  2. What efficiency do you plan at, and what does your line actually achieve?
  3. How do you track progress during production, and can you show me where my order is?
  4. If I add a detail (tape, side seams, an extra label), how many minutes and how much does it add?

A factory that answers these quickly knows its costs and its capacity.

How do we track it?

At our factory every bundle carries a QR ticket that is scanned through every operation, and on a video call you can direct the camera to any machine or bundle. The system is Scan ERP, built by our CEO and also offered to other garment factories, so read that recommendation with that in mind. More on how this cuts waste and delays: reducing fabric waste and tracking line efficiency.

Frequently asked

What is SMV in the garment industry?
SMV, the standard minute value, is the time a trained operator needs to complete a garment or one operation at a normal pace, usually including allowances for rest and machine handling. A factory adds up the SMV of every operation to get the minutes needed for one garment.
Is SMV the same as SAM?
Often, but not always. Many factories use SAM (standard allowed minute) and SMV for the same thing: the standard time including allowances. Others use SMV for the basic time before allowances and SAM for the time with allowances added, so ask whether the figure you are given includes allowances.
What is line efficiency in a garment factory?
Line efficiency compares the standard minutes produced with the minutes actually worked: pieces produced × SMV, divided by operators × minutes worked, × 100. Factories usually plan production at around 60–80% efficiency, because real lines lose time to changeovers, waiting, breakdowns and absence.
How does SMV affect the price of a garment?
The making (CMT) part of a price is roughly the garment’s SMV multiplied by the factory’s cost per minute, adjusted for its real efficiency. More operations mean more minutes, so details like neck tape, side seams or a placket raise the making cost.
SR

About the author

Santosh Rijal runs Trishakti Apparel, the export knitwear factory his family built on three decades in Nepal’s fashion trade. He writes about sourcing, duty and production from the factory floor in Gaindakot.

LinkedIn ↗

Sources & last verified

Page facts checked

We link every trade claim to the body that publishes it — official sources first. Rules change; if you spot something out of date, tell us.

  1. 01 Standard minutes (SAM or SMV) for a few garments: reference values for basic garments Online Clothing Study · checked 25 Nov 2026
  2. 02 Why do garment manufacturers plan production at less than 100% efficiency (some plan at 60%, some at 80%) Online Clothing Study · checked 25 Nov 2026

Keep reading

Namaste — let’s talk

Tell us what you want to make.

Send a tech pack, a photo or just an idea. You’ll hear back from the people who run the floor — usually within 24 hours, Nepal time.

Try Nepal 10% off your first order · free samples · from 200 pieces per colour. How it works

No WhatsApp and rather not email? Request a call-back and we’ll phone you.

Request a quote WhatsApp